• When a change is made to the protection criteria value, such as changing the value from .85 On to 100 mV, creating a history record with an Effective Date identifying when the change occurred allows you to maintain a history for all readings with .85 On prior to the Effective Date, as well as all readings with 100 mV after the Effective Date. Creating a history record in this case is important because the facility may meet the 100mV criterion but fail the .85 On criterion. If history records do not exist, changing the criteria may show readings that were previously within criteria, are now out of criteria.
• You remove a casing and want to document that you are no longer recording Casing P/S inspection readings. Instead of disabling the Activate Casing P/S field in the Information grid, create a history record instead. History records provide useful data for an audit or compliance review.
• When you create a history record, all fields in the original record copy to the new record. Both records are initially the same except for the Effective Date. This allows you to change only the field(s) that are different in the new record and also create a history trail that includes the previous record.
• Do not enter the date a facility was put into service as the Effective Date. Use the Effective Date field to enter a date when a facility is taken out of service; when a change is made to the protection criteria; or when a facility is made inactive. Effective Date is used only with history records; it is empty in the original facility record. When a facility is put into service, add the date in the field labeled Installation Date.
• To help with using history records consistently, enable the field labeled Warm Before Permanent History Record Changed Option in Options (Tools > Options). When enabled, PCS Axis displays a warning message stating a history record should first be created before making changes.
1 Select one or more pipeline segments in the Select ROWs window (Figure 7-4). Choose pipeline segments with facilities you want to work with, then clickSave to close the window.
2 Open the Edit <module> Data window. For example, click Data Entry > Edit CPDM Data to open the Edit CPDM Data window (Figure 7-26).
3 Open the Information grid for a facility type. For example, click the Information taband then a facility type button, such as Test Point
.
4 If you want to collapse the Selected ROWs panel to view more of the grid, click the Selected ROWs bar. Clicking the bar again expands the panel.Figure 7-26. Test Point Information Grid
5
6 Click the option Test Point Information Record.
7 Select a facility record in the Add Record dialog box that you want to create a history record. For example, the facility record with Relative Milepost 1.627 is selected in the following figure (Figure 7-27).Figure 7-27. Add Record
8 PCS Axis adds a new record in the Information grid for the selected facility with today’s date showing in the Effective Date field. The Facility Active check box is also enabled by default in order for the facility to be included in facility survey schedules. The original record becomes the history record (Figure 7-28).
•
• Click the Facility Active check box to remove the check mark and subsequently deactivate the facility.
• As a recommendation, enter a comment in the Permanent Comments field about the record change.Figure 7-28. Test Point Information Grid